The court disposed of two writ petitions seeking conversion of electricity service connections from commercial to agricultural tariff. It directed the petitioner to pay outstanding arrears for the first case before the Board considers the reconversion application.
What did the court decide?
Petitioner directed to pay remaining arrears of Rs.8,497 within four weeks. Upon payment, respondents to consider reconversion application within 30 days.