K.Marappan Gounder v. the Junior Engineer
Case brief
What is this about?
The petitioner, running a cottage industry, challenged a demand notice for electricity arrears, claiming entitlement to subsidised rates under G.O.Ms.No.3042. The Court dismissed the petition, holding the petitioner ineligible for subsidies as his industrial unit and residence were not located in the same place. The petitioner was directed to pay the balance demand.
What did the court decide?
Petitioner directed to pay balance demand of Rs.63,608/- to the Electricity Board within three months.