M/S.Arkay Energy (Rameswaram) v. the Govt. of Tamil Nadu
Case brief
What is this about?
The Madurai Bench disposed of a writ petition challenging the minimum bid capacity of 100 MW in a tender for power procurement. The court held that while tenders should proceed, the respondents must approach the Tamil Nadu Electricity Regulatory Commission to resolve the capacity shortfall to safeguard public interest.
What did the court decide?
Petition disposed; respondents directed to proceed with bid processing and approach TNERC within two days to resolve capacity shortfall.