Immanuel Crushers & Mines (P) Ltd. v. State of Kerala
Case brief
What is this about?
Single-judge Kerala High Court writ disposal granting instalment facility for mining dues: quarrying lease, demand notice DOPAL-DMG/791/2023/M dated 27.03.2025, six equal monthly instalments from 07.05.2025, coercive recovery in abeyance, KOMPAS (Kerala Online Mining Permit Awarding Services) portal reopening after first instalment, resumption of recovery on two consecutive defaults; parties: Immanuel Crushers & Mines (P) Ltd v. State of Kerala (Dept. of Industries) and The Geologist, Dept. of Mining and Geology, Palakkad; counsel: Enoch David Simon Joel and team for petitioner; Rajeev Jyothish George, GP for respondents.
What did the court decide?
Permission granted to pay the amounts due under Ext.P2 demand notice in six equal monthly instalments (first on or before 07.05.2025, subsequent instalments on or before the 7th of succeeding months); coercive recovery steps kept in abeyance during the instalment plan; KOMPAS portal to be opened after the first instalment; respondents free to resume recovery proceedings upon two consecutive defaults.