M/S.Mallelil Industries Pvt. Ltd. v. the Assistant Executive Engineer
Case brief
What is this about?
The petitioner challenged a notice demanding payment of centage value for a bridge constructed over a thodu. The court found the notice violated natural justice due to the lack of prior notice and hearing, ordering the respondent to treat the document as a notice and decide within two months after affording an opportunity to be heard.
What did the court decide?
Directed respondent to treat Ext. P7 as notice, provide time for reply, and decide within two months of judgment copy after hearing opportunity.