Kerala Water Authority Represented by Its Managing Director v. Reena Engineers and Contractors Pvt. Ltd. 602
Case brief
What is this about?
The Kerala High Court reviewed an order directing payment to a contractor. The court rejected the argument that the lack of a specific PWD accounts code provision for Bank Guarantee payments was fatal, noting the transaction was consensual and balanced interests. An extension was granted for compliance.
What did the court decide?
Review petition closed, but time for compliance with the original order extended by two months.