Abi Itty Jacob v. the State of Kerala
Case brief
What is this about?
Petitioners sought demolition of a traffic system installation causing shop obstruction and drainage issues. The Court noted unclaimed cables hindered drainage work. It directed the Corporation to complete drainage reconstruction within three months, dispensing with further adjudication on the traffic system.
What did the court decide?
Direction to the 6th respondent-Corporation to complete the drainage reconstruction process within a period of three months.