Haskar.M v. Perinthalmanna Municipality
Case brief
What is this about?
The High Court of Kerala disposed of two writ petitions regarding non-payment of contract bills by the Petintalmanna Municipality for completed public works, directing immediate payment of 50% dues within three months.
What did the court decide?
Directing the respondents to pay 50% of the amounts due to petitioners within three months and the balance 50% within a further period of three months.