Reena Engineering and Contracting Company Ltd. v. Kerala Water Authority
Case brief
What is this about?
In a writ petition regarding a construction contract dispute over rate revision, the court examined the powers of the KIIFB Inspection Authority. It held that the Authority could examine the Board's rejection independently and directed the Chief Project Examiner to make a recommendation following prescribed guidelines.
What did the court decide?
Directed the 5th Respondent (Chief Project Examiner) to consider the petitioner's representation uninfluenced by the Board's prior decision and to make an appropriate recommendation within three month