Krishna Engineering v. Commander Works Engineer
Case brief
What is this about?
Writ petitioner, an enlisted contractor, approached the Court for direction to pay the approved bill amount owing for construction work completed in 2020. The Court observed no justification for the delay, particularly after bilateral approval, and directed the ER3 to pay.
What did the court decide?
Directing the 3rd respondent to pay the bill amount approved as per Ext. P5 within three months of receipt of a copy of this judgment.