utilizing crores of expenditure. As per this project, 10 MLD of water to be supplied to Puthuvype pump house from Vaduthala. But project did not meet the demands and serve the purpose of the scheme to the inhabitants of Vypin Island. Hence another two projects namely, 1) GIDA Aided water Supply Scheme to Elamkunnappuzha, Njarakkal and Nayarambalam and 2) Chowara project, for the rest of the area including Edavanakkad Panchayat, with a view to maintain and ensure equitable water supply in Vypin Island was sanctioned and started the work before 10 years. But, due to the inaction and lethargy of the respondents the GIDA project have not commissioned so far even though crores of Rupees have been spent. As per the GIDA Aided water Supply Scheme to Elamkkunnapuzha, Njarakkal and Nayarambalam, water being pumped from Puthuvype Pump House (collected from Vaduthala) will be utilized for the southern Panchayats namely Elamkunnapuzha, Njarakkal and Nayarambalam. According to the Kerala Water Authority this project is fulfilling the demands of water up to 2041.