V.G.S. Enterprises v. Indian Oil Corporation Ltd.
Case brief
What is this about?
In a writ petition filed by a contractor against Indian Oil Corporation, the High Court directed the competent authority to constitute a committee and consider the petitioner's representation regarding delayed work and deducted liquidated damages within three weeks, thereby disposing of the petition.
What did the court decide?
Direction to the competent authority to constitute a two-member Committee to consider the representation on liquidated damages and take a final decision within three weeks.