Cas Castles Engineers and Builders v. Valsa Jose
Case brief
What is this about?
This judgment allows original petitions of specific performance and sets aside trial court orders directing petitioners to complete additional works. The court held the lower court exceeded jurisdiction by going beyond the settlement terms to ignore the agreement's scope regarding completion certificates.
What did the court decide?
Original petitions allowed; impugned orders in I.A.No.4395/2018 and E.P.No.10/2019 set aside; remanded for fresh orders based on settlement terms.