What is this about?
The petitioner, a PWD contractor, sought to have pending bill amounts adjusted against his Performance Guarantee as the EMLI software was non-functional. The Court directed the respondents to manually process the adjustment within three weeks and extended the execution timeline.
What did the court decide?
Direction to adjust pending bill towards Performance Guarantee manually within 3 weeks; extension of time for agreement execution by 2 weeks.