Sri Varalakshmi Agencies, v. Union of India
Case brief
What is this about?
Petitioner contractor challenged the quality test results of steam coal supplied to the 2nd and 3rd respondents. The High Court directed the 3rd respondent to finalize the petitioner's request for third-party testing within three weeks, allowing time for hearing and document consideration.
What did the court decide?
Direction to 3rd respondent to finalize representation (Ext.P12) for third-party testing within three weeks, after hearing petitioner and examining documents.