P.B.Dinesh Kumar, v. Cochin Devaswom Board
Case brief
What is this about?
A contractor sought release of security deposit withheld by the Executive Engineer of the Cochin Devaswom Board. The High Court directed the Executive Engineer to finalize the petitioner's representation and release the deposit unless legal inhibitions exist.
What did the court decide?
Directed the 3rd Respondent to finalize Ext.P3 within three weeks and release the security deposit forthiften there are no legal inhibitions.