11.12.2018 is concerned, it is stated that, tenders are invited for supply of GI Earth Wire 7.35 mm (150 kms) and 7.366 mm (40 kms). The said tender was a single bid system. Four firms namely M./s Malu wires, Bangalore–9, Nirmala Wires Pvt. Ltd, Kolkatta–39, Krithika Wires Ltd, Kolkatta and the 1st petitioner herein participated in the said tender. In regard to the 1st petitioner, certain documents were found missing and also deviation from the tender specifications were noted. Accordingly, as per Ext.R2(a) communication dated 28.01.2019, the 3rd respondent addressed the petitioner requesting him to furnish missing documents and to withdraw the deviations found in the offer. As per Ext.R2(a), the 1st petitioner had to comply with the request on or before 31.01.2019. But the 1st petitioner failed to respond to the same within the stipulated time, which compelled the respondents to proceed with the tender submitted by other tenderors. However, the said tender is not yet finalized. Therefore, according to the respondents, petitioner has no real grievance to secure any relief from this court and the 2nd petitioner had never submitted any tender in