K.P. Anilkumar v. State of Kerala
Case brief
What is this about?
The High Court disposed of a writ petition filed by a contractor seeking return of a security deposit and a direction to consider a proposal for cost escalation regarding a construction contract. The Court held that the subject matter was not finalized and directed the 2nd respondent to consider the proposal after a hearing within a month.
What did the court decide?
Directed the 2nd respondent to finalize the Ext.P10 application submitted by the petitioner after providing an opportunity of hearing within one month from the date of receiving a copy of the judgment