P. Sasikala v. Thiruvananthapuram Corporation
Case brief
What is this about?
The High Court held that a pending Master Plan under a repealed Act remains in force until superseded by the Kerala Town and Country Planning Act, 2016. However, since the two-year acquisition period under Section 67 of the new Act has lapsed, the petitioner's offer to sell requires a decision within sixty days. The Court granted the Corporation three months to decide on purchase; failing this, th
What did the court decide?
Three months granted to the Corporation to decide on acquisition; if no decision is made, the building permit application shall be processed within one month thereafter.