P.Abdul Rasak v. the State of Kerala
Case brief
What is this about?
The Division Bench upheld the termination of the contractor's contract but set aside the order for recovery of tentative loss. The court directed the Government to re-visit the estimation, ascertain actual loss suffered after giving the contractor an opportunity to be heard, and pass a fresh order within six weeks.
What did the court decide?
Direction to re-visit Ext.P19 estimation, ascertain actual loss after giving the contractor an opportunity to be heard, and pass a fresh order within six weeks.