Bharati Infratel Ventures Ltd. v. Corporation of Thrissur
Case brief
What is this about?
The High Court disposed of a writ petition challenging a final electricity assessment order. Instead of adjudicating the factual dispute, the Court directed the petitioner to prefer an appeal before the competent appellate authority under Section 127 of the Electricity Act, 2003 and kept the demand in abeyance.
What did the court decide?
Petitioner granted four weeks to prefer appeal; appellate authority to decide within three months; balance demand kept in abeyance.