Kitco Ltd. v. K.S.E.B
Case brief
What is this about?
The Court disposed of a writ petition challenging a demand for transmission side costs for an office electricity connection. While noting that the matter was pending before the Consumer Grievance Disputes Redressal Forum, the Court granted a one-month grace period to approach the Forum and made the payment liability subject to that outcome.
What did the court decide?
Petitioner granted one month to approach CGDRF to challenge the demand; liability to pay demand subject to CGDRF orders.