M/S.Mary Matha Construction Company v. State of Kerala
Case brief
What is this about?
The petitioner, a contractor, filed a writ petition seeking release of sanctioned payment withheld by the Irrigation Department due to a vigilance investigation and a dispute over material usage. The Court directed the respondents to disburse the approved amount within one month.
What did the court decide?
Respondents directed to disburse the amounts covered by Bill No.18779/2015-16 dated 28.02.2016 within one month.