M/S.Southern Tech Engineering Contractor v. State of Kerala
Case brief
What is this about?
In this writ petition regarding work contract rates, the Court observed that delays in site handover and non-attrinable to the contractor justified a rate revision claim despite supplementary agreements. The Government was directed to reconsider the claim following a prior judgment.
What did the court decide?
Ext.P9 order set aside; Government directed to reconsider petitioner's claim for rate revision within three months.