Rr Holiday Homes Pvt.Ltd v. K.S.E.B, Rep. by Its Secretary
Case brief
What is this about?
The court held that an appellate authority is now constituted following Muhammad Haji. The petitioner is directed to file an appeal under Section 127 of the Electricity Act, 2003 within one month, which will be disposed of within three months. Recovery steps are stayed pending this appeal.
What did the court decide?
Allowed; Appeal directed to be filed within one month; recovery steps stayed.