T.S. Venkateswaran v. Asst.Engineer, K.S.E.B.
Case brief
What is this about?
The petitioner alleged a faulty electricity meter causing excessive charges. The Court held the Board failed to follow statutory procedures. Directing a new meter assessment, the Court ordered a revised bill calculation based on six months' average consumption and six instalments for arrears.
What did the court decide?
Board to assess average consumption for six months post-new meter, issue revised bill including arrears from initial disputed bill, and allow payment in six instalments.