M/S.Hardi Trebers v. K.S.R.T.C.
Case brief
What is this about?
In an appeal against a judgment granting a 3-day grace period and 6% interest on unpaid supplies, the High Court held that the lower court erred in modifying the original 10-day contract. The appeal was partly allowed, affirming 6% interest from the notice date but modifying the decree to allow realization of the specific adjusted amount.
What did the court decide?
Appellants allowed to realise `1,61,311/- with interest at 6% per annum from 15/06/1999 till realization, with costs.