This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR.JUSTICE ANTONY DOMINIC
WEDNESDAY, THE 13TH DAY OF FEBRUARY 2013/24TH MAGHA 1934
AR.No. 33 of 2012
PETITIONER(S)/PETITIONER/APPLICANT:
KURIAN & VARGHESE
ENGINEERS AND CONTRACTORS, THACHAMPURATH MULANTHURUTHY-682314 ERNAKULAM DISTRICT.
BY ADVS.SRI.MEIJO KURIAN PUVATHINGAL
SMT.PREMY MEIJO
RESPONDENT(S):
BY . SRI.P.PARAMESWARAN NAIR,ASG OF INDIA
THIS ARBITRATION REQUEST HAVING BEEN FINALLY HEARD ON 13-02-2013, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:
AR.No. 33 of 2012
APPENDIX
ANNEXURES
A1TRUE COPY OF THE ARBITRATION CLAUSE NO.70 AS PROVIDED IN THE GENERAL CONDITIONS OF CONTRACT OF THE MES (IAFW 2249) FORMING PART OF THE CONTRACT AGREEMENT
A2TRUE COPY OF THE NOTICE ISSUED DATED 3.10.11 TO THE ENGINEER -IN-CHIEF OF MES ARMY HEAD QUARTERS, NEW DELHI ALONG WITH THE TERMS OF REFERENCE REQUESTING FOR THE APPOINTMENT OF A SOLE ARBITRATOR
R1(a)- TRUE COPY OF THE SCHEDULE A NOTE SHOWING THE RELEVANT CONTRACT STIPULATION
R1(b)- TRUE COPY OF THE LETTER DATED 27.3.12
R1(c)- TRUE COPY OF THE LETTER DATED 31.5.12
R1(d)- TRUE COPY OF THE CERTIFICATE DATED 27.11.10
/true copy/
sd/- P.A. To Judge
mrcs
ANTONY DOMINIC, J
A.R.33/2012
Dated this the 13th day of February, 2013
ORDER
In view of the order dated 13.2.2013 in R.P.82/2013, the
Arbitration Request will stand dismissed.
Sd/- ANTONY DOMINIC, JUDGE
mrcs
/true copy/
sd/- P.A. To Judge
KURIAN & VARGHESE ENGINEERS AND CONTRACTORS
THE CHIEF ENGINEER, (N.W.) NAVAL WORKS
ANTONY DOMINIC
As recorded by the court registry
Judgements on the same questions, provisions and authorities, from every court