Muhammed Ali v. Kavulumpara Grama Panchayath
Case brief
What is this about?
Petitioner sought payment for constructed school building work. Court directed petitioner to apply for time extension; Panchayath to pay due for completed work within 3-6 months after application.
What did the court decide?
Direct petitioner to apply for time extension within 10 days; direct Panchayath to pay due amount for completed works within 3-6 months after application.