K.Gopi v. the Secretary, Varapetty Grama Panchayt
Case brief
What is this about?
The Court held that a contractor entitled to recover excess material costs under a Government Order incorporated into the agreement, even if the tender quote matched the estimate rate, directing the Panchayat to sanction bills within a month.
What did the court decide?
The petitioner is declared entitled to the benefit of the Government Order; the 2nd respondent to sanction the bills within one month.