Yudhir Varma.R... v. Gokulam Engineers India.
Case brief
What is this about?
Petitioners challenged a land acquisition notification for a new bridge construction. The Court examined proposals from petitioners and the Government regarding exempting specific shop rooms. The writ petition was closed after recording submissions that the matter would be addressed during implementation and no further specific reliefs were sought to be granted immediately.
What did the court decide?
The Writ Petition is closed after recording the submission that the matter would be looked into at the time of actual implementation and to the extent possible, the interests of the petitioners would