Smt. Kavitha Muppiri v. Bangalore Electricity Supply Company Limited
Electricity – Disconnection threat
Case brief
What is this about?
BESCOM disconnection notice without jurisdiction; Grama Panchayat NOC demand; unauthorised construction allegation; existing electricity connection protected; Apex Court occupancy/completion-certificate directions held prospective ('shall' applies to new connections only); Sri Nagabhushana v. Chief Executive Engineer (W.P.17679/2024 c/w 26870/2023) followed; Rajendra Kumar Barjatya explained via Co-ordinate Bench; construction permissions exclusively local authority's domain; Articles 226/227 writ; certiorari; Articles 14, 19(1)(g), 21 invoked; paying guest (PG) premises; Karnataka High Court, Bengaluru; Lalitha Kanneganti J.; WP No.21035 of 2026 (GM-KEB); notice set aside, petition allowed, IAs closed.
What did the court decide?
Writ petition allowed; notice dated 03.07.2026 issued by respondent No.2 (Annexure-A) set aside; pending IAs, if any, stand closed.