Ms. a Mohana Preethi v. Bangalore Electricity Supply Company Limited
Case brief
What is this about?
Karnataka High Court, Bengaluru (Smt. Justice Lalitha Kanneganti), WRIT PETITION NO. 20242 OF 2026 (GM-KEB), decided 06.07.2026 — petition under Articles 226/227 by apartment-project landowners (through GPA holder M/s. SLV Building Generations) challenging BESCOM letter dated 17.06.2026 (No. P.SM.SKE(V)/SE(T)/P4/25-26/659) demanding a BBMP NOC within seven days, and against unilateral disconnection of the electricity connection on 01.07.2026 without any final order on the show cause notice; supply restored via interim order dated 03.07.2026; petition disposed of with directions to file a reply within two weeks, adjudication in accordance with law, and no disconnection in the interim. Search terms: BESCOM; electricity disconnection; show cause notice; BBMP NOC; temporary electricity connection; Joint Development Agreement; writ of certiorari; writ of mandamus; restoration of power supply; natural justice; Articles 226 and 227.