Shri v. Srinivas Redy v the Union of India
Case brief
What is this about?
Maintainability of writ petition where arbitration clause exists in tender documents; termination of letter of intent for linen washing contract (South Western Railway, Bangalore Division); dismissal with liberty to pursue arbitration under the Arbitration and Conciliation Act, 1996; Articles 226 and 227 Constitution of India; termination notice 06.12.2025 No. B/M.271/Cont/Linen/Washing/SBC; Karnataka High Court 2025; Justice Suraj Govindaraj; WP 37832 of 2025 (GM-TEN).
What did the court decide?
No substantive relief; petition dismissed with liberty reserved to the petitioner to initiate proceedings under the Arbitration and Conciliation Act, 1996. ¶38