Sri.P. Vijay @ Viojayraj v. the Assistant Executive Engineer
Electricity disconnection – Unauthorised construction
Case brief
What is this about?
Karnataka High Court (Bengaluru), Writ Petition (GM-KEB) No. 29456 of 2025, disposed 25.09.2025 by Justice Ravi V Hosmani. Petitioner Sri P. Vijay @ Viojayraj s/o Palayan vs BESCOM (AEE East Division-01; AE Bensen Town) and BBMP (Chief Commissioner; AEE Vasanth Nagar Sub-Division 3). Quashing of BESCOM letter dated 04.07.2025 bearing No. SA.KAA.NE. M(V)/E-1/SA.AA.(T)/572 (Annexure-A); power supply restoration/meter refixation sought for meters RR 1EEH 58933 to 58938; appeal pending before Commissioner under Bruhat Bengaluru Mahanagara Palike Act 2020; Articles 226 & 227 Constitution of India; cites Rajendra Kumar Barjatya and Another v. U.P.Avas Evam Vikas Parishad and Others, 2024 SCC OnLine SC 3767 (para 21 directions); advocates Bhuvan K.P. (petitioner), H.V. Devaraju (R1-R2), Pawan Kumar (R3-R4).
What did the court decide?
Letter at Annexure-A discharged (no disconnection action taken); respondent no.2 directed to continue power supply meanwhile subject to payment of consumption/advance consumption charges; respondent no.3 directed to dispose of the pending appeal within two months mindful of the SC directions in para 21 of Barjatya's case and to intimate the result to respondent no.2; liberty reserved to respondent no.4 to act after appeal disposal.