Shri.Murali Dorai v. Bengaluru Electricity Supply Company Limited
Case brief
What is this about?
Writ petition under Articles 226 & 227, Constitution of India; certiorari against BESCOM notices (Annexures-W and X); power supply disconnection/restoration; unauthorised construction; occupancy certificate; Sections 248(1) and 248(3) BBMP Act orders under appeal before Commissioner, BBMP; action pending appeal not justified; time-bound disposal of appeal (two months); Supreme Court directions in Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad, 2024 SCC OnLine SC 3767, para 21; continuation of power supply subject to consumption charges; BESCOM Dooravaninagar Sub Division; BBMP; Karnataka High Court, 25.09.2025.
What did the court decide?
Notices dated 14.05.2025 and 17.07.2025 (Annexures-W and X) discharged with liberty to respondent no.4 to act after disposal of the appeal; respondent no.4 to continue power supply subject to payment of (advance) consumption charges; respondent no.6 to dispose of the pending appeal within two months keeping in mind the Supreme Court's directions in para 21 of Rajendra Kumar Barjatya (supra) and intimate the result to respondent no.4.