The Deputy Chief Engineer v. the President
Case brief
What is this about?
Keywords: land acquisition enhancement; Section 54(1) appeal by beneficiary; Section 23(1-A) additional market value 12% per annum; Section 34 interest 9% and 15%; Section 4(1) preliminary notification dated 09.01.2009; possession 31.01.2010; award 11.06.2010; Rs.7,27,095/- per gunta; 30% solatium under Section 23(2); reference under Section 18 allowed in part; South Western Railway Deputy Chief Engineer (Construction Central) Hubballi; Arogya Nagar Gruha Nirmaan Sahakari Sangh (Regd), Dharwad; Assistant Commissioner and Land Acquisition Officer, Dharwad; L.A.C. Nos. 159/2011, 07/2013, 09/2013; M.F.A. Nos. 100834-100836 of 2018; earlier M.F.A. No.101329/2018 partly allowed 18.11.2020; correction of statutory benefits; II Addl. Senior Civil Judge, Dharwad; High Court of Karnataka, Dharwad Bench; neutral citation NC: 2025:KHC-D:10000-DB.
What did the court decide?
All three appeals (M.F.A. Nos. 100834, 100835 and 100836 of 2018) allowed in part: the impugned judgment and award dated 23.03.2017 stands modified so that additional market value at 12% p.a. under Section 23(1-A) is confined to the period 09.01.2009 (preliminary notification) to 31.01.2010 (taking of possession), and interest runs at 9% per annum from 31.01.2010 for one year and at 15% per annum thereafter until deposit of compensation under Section 34; pending IAs disposed of.