The Executive Engineer v. Mr M.P. Nrupathunga
Case brief
What is this about?
Commercial appeal; arbitration; Section 34 application partly allowed; modification of arbitral award dated 17.10.2023; summary disposal without reasons; remand under Section 37; Gayatri Balasamy v. ISG Novasoft Technologies (2025 SCC OnLine SC 986); Bombay Slum Redevelopment Corporation v. Samir Narain Bhojwani ((2024) 7 SCC 218) para 29; damages Rs.4,00,000/-; limitation for damages not considered; Commercial Court Bengaluru CCH-85; PWD Karnataka State appellants; judgment dated 30.03.2024 set aside; fresh consideration; appearance on 19.01.2026.
What did the court decide?
Appeal allowed; impugned order dated 30.03.2024 in Com.A.P.No.198/2023 set aside; matter remitted to the Commercial Court to consider the commercial application filed by the respondent on merits and in accordance with law after providing sufficient opportunity to the parties; appellants and respondent to appear before the Commercial Court on 19.01.2026.