Mr Azamthullah a v. Bescom Electricity Supply Co. Ltd.
Case brief
What is this about?
Petitioners sought to quash an endorsement denying electricity connection due to an interim order in a related matter concerning construction compliance. The court held that since the related writ petition was disposed of and construction complied with plans, denial was unjustified.
What did the court decide?
Quashed the endorsement denying supply; directed Respondent No.2 to continue permanent/temporary power connection and consider permanent sanction application within four weeks.