The Chief Engineer v. M/S. v.U.Seemon Engineers and Contractors
Case brief
What is this about?
This High Court dismissed a civil revision petition challenging an execution court order directing payment of a large sum including interest. The court rejected the argument that calculating interest on interest is impermissible, relying on recent Supreme Court precedents which hold that once principal and interest merge into a single due sum, they cannot be segregated for calculation purposes.
What did the court decide?
Revision petition dismissed; order of the trial court upholding the memo of calculation affirming the payment of Rs.14,61,026.30 including interest.