M/S Spg Systems v. the Managing Director (Electrical)
Case brief
What is this about?
Petitioner challenged BESCOM's communication requiring an occupancy certificate for additional electrical load. Court held a KERC notification deleted this requirement. Impugned communication was quashed, and service of additional load was directed.
What did the court decide?
Impugned communication quashed; third respondent directed to provide additional load of 200 KVA forthwith.