Sankayya Shetty v. State of Karnataka
Case brief
What is this about?
The High Court of Karnataka examined a plea challenging the cancellation of a quarry lease notification. It held that non-execution of the lease within six months leads to automatic revocation and clarified the Competent Authority's power to extend this period. The petition was disposed of by granting the petitioner time to apply for an extension.
What did the court decide?
Petitioner allowed one month to apply to the Competent Authority for an extension of the lease period.