This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
M.F.A.No.1053/2019
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 26TH DAY OF OCTOBER 2021
BEFORE
THE HON’BLE MRS JUSTICE K.S.MUDAGAL
MISCELLANEOUS FIRST APPEAL NO.1053/2019 (LAC)
BETWEEN:
A.B.NEMICHANDRAPPA S/O. BHARMAGOWDA MAJOR R/AT HATTUR VILLAGE HONNALI TALUK DAVANAGERE DISTRICT REP. BY HIS GPA HOLDER V.NARAYANA S/O. VENKARACHALA R/AT GADIKOPPA LAYOUT WARD NO.35, SHIMOGA …APPELLANT
(BY SRI SANGAMESH.G.PATIL, ADVOCATE [ABSENT])
AND:
THIS MFA IS FILED UNDER SECTION 54(1) OF THE LAND ACQUISITION ACT AGAINST THE JUDGMENT AND AWARD DATED 12.12.2012 PASSED IN LACT NO.27/2010 ON THE FILE OF THE SENIOR CIVIL JUDGE, HARIHAR, PARTLY ALLOWING THE CLAIM PETITION FOR COMPENSATION AND SEEKING ENHANCEMENT OF COMPENSATION.
M.F.A.No.1053/2019
2
THIS MFA COMING ON FOR ORDERS THIS DAY, THE COURT DELIVERED THE FOLLOWING:
J U D G M E N T
No representation for the appellant. The
peremptory order dated 26.02.2020 is not complied.
Therefore, the appeal is dismissed.
Sd/JUDGE
pgg
A.B.Nemichandruppa S/O. Bharmagowda (Rep. By V.Narayana S/O. Venkarachala)
The Special Land Acquisition Officer, UTP, Shimoga
The Executive Engineer Neeravari Nigama Niyamitha Irrigation Department No.5, Honnalli
K.S. Mudagal
As recorded by the court registry