M/S R. K. Infra (India) Pvt. Ltd. v. the Secretary
Case brief
What is this about?
Under Section 11(6) of the Arbitration and Conciliation Act, 1996, the High Court ordered the appointment of a sole arbitrator for a construction dispute. The Court allowed the petition despite the respondents' argument that the dispute was stale because the petitioner approached the Court beyond the 30-day limit stipulated in the contract.
What did the court decide?
Petition allowed to appoint Sri. Venkatasudarshana as the sole arbitrator. All contentions regarding the validity of termination and time-bar are left open for arbitration.