M/S Jharkhand State Building Construction Corporation Ltd., through Its Executive Director, v. the State of Jharkhand Thr. the Director Industries-Cum-Chairman
Case brief
What is this about?
Interim relief refused; stay of execution of arbitration award dated 27.05.2022; no Section 34 Arbitration and Conciliation Act 1996 challenge; delayed Article 226 writ petition filed only in 2025; Bihar and Orissa Public Demand Recovery Act 1914 recovery certificate; discretionary refusal of interim relief held not vitiated for judicial review; appeal dismissed without costs; Jharkhand HC L.P.A. No. 669 of 2025, decided 24.02.2026; Bench: M. S. Sonak, C.J. and Rajesh Shankar, J.; appellant M/s Jharkhand State Building Construction Corporation Ltd.; respondents include State of Jharkhand (Director, Industries-cum-Chairman, MSME Facilitation Council), M/s Ranchi Design & Consultancy Service Pvt. Ltd. and Jharkhand Education Project Council.
What did the court decide?
There is nothing on record to show that the award dated 27.05.2022 was challenged under Section 34 of the Arbitration and Conciliation Act, 1996; the writ petition was filed only in 2025, after the award holder obtained a recovery certificate and the execution proceedings had begun.