Banshidhar Construction Pvt. Ltd., through Its Chief Executive Officer, Kanchan Yadav v. the State of Jharkhand, through the Secretary, Dept. of Mines and Geology
Case brief
What is this about?
Jharkhand High Court, Ranchi; W.P.(C) No. 5897 of 2025 (decided 11.11.2025); Banshidhar Construction Pvt. Ltd. v. State of Jharkhand; sand mining; cancellation of Letter of Intent nos. 413, 414, 415 dated 21.02.2024 and agreements dated 04.03.2024; letter no. 1058 dated 01.08.2025; JSMDC / In-charge Sand-I; sand deposits Urali, Bahera, Kedalikalan, Patwa, Banki, Kobni, Sahi in Chatra district; refund of performance and additional security; public hearing; issue covered by co-ordinate Bench judgment in batch led by W.P.(C) No. 4503 of 2025; writ petition dismissed; parties to bear own costs.
What did the court decide?
No relief granted; parties left to bear their own costs. ¶23