Sunil Kumar v. State of Jharkhand And Ors.
Case brief
What is this about?
Jharkhand High Court (W.P.(C) No. 2270 of 2012, decided 19.03.2024, Gautam Kumar Choudhary, J.): Article 226 writ by Assistant Engineer for recovery of Rs.58,78,920/- withheld as excess expenditure on construction of Community Health Centre, Barkatha, dismissed; writ jurisdiction unavailable for money claims arising out of breach of contract and for disputed questions of fact on accounts; Hindustan Petroleum Corpn. Ltd. v. Dolly Das, (1999) 4 SCC 450 relied on. Keywords: money claim, breach of contract, disputed question of fact, advance adjustment, unadjusted amount, writ dismissal.
What did the court decide?
Extraordinary writ jurisdiction cannot be invoked for money claims arising out of breach of contract, even against the State; consequently the petitioner's money claim cannot be pursued through this writ petition. ¶26