Bonafide Himachalis Hydro Power Developers Association v. Union of India and Others
Case brief
What is this about?
HP High Court Shimla | Ex. Pet. No.1963 of 2025 | execution petition disposed 10.07.2026 | Bonafide Himachali's Hydro Power Developers Association v. Union of India | uniform RoW width transmission lines forest land | Notification 05.05.2014 | order 16.04.2018 in CWP No.4450 of 2015 | MoEF refused RoW relaxation, meeting 03.04.2019 | Guidelines 05.05.2014 revised vide Comprehensive Guidelines 08.03.2019 | Letter 31.05.2019 Annexure R-1 | nothing survives for adjudication in execution | liberty to challenge afresh if permissible.
What did the court decide?
The decision on the issue has already been taken (the Ministry of Environment and Forests having declined RoW relaxation and the Guidelines dated 05.05.2014 having been revised vide Comprehensive Guidelines dated 08.03.2019), and therefore nothing survives for adjudication in execution.