Kamla Devi v. Land Acquisition Officer-Cum-Competent Authority Under NHAI and Another
Case brief
What is this about?
The High Court of Himachal Pradesh addressed an arbitration dispute arising from land acquisition for National Highway development. The court observed significant delays by the arbitrator causing potential termination of mandate under Section 29-A. Relying on Supreme Court guidance regarding time limit extensions, the court allowed the petitions and ordered the arbitrator to conclude proceedings b
What did the court decide?
Petitions allowed; arbitrator directed to conclude arbitration proceedings on or before 08.01.2025 and to provide a timetable for the parties.