Satinder Singh v. State of Hp and Others
Case brief
What is this about?
Arbitration case seeking extension of time for the arbitrator to pass an award, the arbitrator having closed proceedings after failing to decide within the stipulated period. The Court extended the period for completing arbitration proceedings by six months from the date of order.
What did the court decide?
Period for completion of arbitration proceedings extended by six months; parties directed to appear before the learned Arbitrator on 26.07.2024.